Tuesday 29 June 2021

Gates and Lights

 

Aluminium Gates in Anthracite Grey.

Welcome to our home! We finally moved in this month. Still bits to do but it's habitable and very pleasant, especially with Summer just around the corner. Here is a selection of external photographs.



SunSeeker UltraSlim doors in anthracite grey

The image above is of the lounge before we cluttered it with our furniture! You can see the log burner reflected in the door glass and the panel blinds we bought on-line, taking a chance on the colour (neutral), and the grey oak laminate flooring. 

We've taken some night time shots, too, showing the external lights through the gates and on the front of the house.



More still to come, including:

  • Internal photographs;
  • New out-building (scheduled for July);
  • Garden project, ongoing... 
Thanks for taking an interest.

Friday 21 May 2021

Update: driveway paved, removal company booked

 


Our lovely light grey paviors are now in place on our driveway hardstanding and the gates have been delivered to be installed next week. Our recycling and rubbish bins have been supplied by the local council and broadband is in.

Packing has begun (about 50 boxes so far) and the removal company has been booked for next month. 

It seems like this is happening, at last!


Friday 14 May 2021

So Close to Moving In!

Just a couple of jobs to finish and our new house will, at last, become our home. 

There were some snagging issues that are being undertaken this week and we have also sorted out the broadband service to the house. The council have delivered our bins, too. 

The driveway hardstanding is ready but the entrance where it meets the road has to be finished once the gate posts are in place - these have been on order with a scheduled delivery date of mid-May (i.e. any time now). 

We have no storage but a wooden shed-studio is due for delivery and erection in July (we're not waiting for that before we move, though). 

The biggest drawback is finding a removal company at a reasonable price who are able to fit us in at the end of this month. We need strong, fit professionals to carry our furniture down the 50 stairs from our flat (no lift) otherwise we might have attempted to hire a van and do the move ourselves. We couldn't book a removal service in advance because the goal-posts were moved on a weekly basis.

Photographs of inside our house (now that the cleaners have been)... 

kitchenkitchen

bathroombathroom

en-suiteen-suite

Now that the house is completed, we'll concentrate on lanscaping - let's hope for a good summer!


Tuesday 20 April 2021

Build completed, Driveway almost completed.

We've lost another month and made more compromises but we are so close! Here is an update since the previous post: 

  • Outside access to accommodate disabled visitors; Nearly...
  • 'Walk-through' and deep clean; Walk-through done, Deep-clean a week away.
  • Address registration with Royal Mail and BT. Done! 
There are now steps from the patio to the base for a wooden out-building:  studio/office/gym/storage/whatever. 


We said goodby to the skip this week ('though I'm sure we'll need another one) and we'll be saying goodbye to the outside loo, too! You can see that the drive has been prepared, ready for the paviors to be completed in the next few days.


Inside the house, all the window blinds are in place.



All we have to do now is to find a removal company with a spare day in the near future - then pack! We hope it's a good long summer so that we can work on the garden (lawn, vegetable patch, flowers, etc.). 

Fingers crossed that the next post will be a happy one! 


Thursday 18 March 2021

Another Month has Dragged on...

We are almost a month further on, time-wise, but not much further than we were in our previous post:

The only things to be finished before we are able to move in are: 

  • Outside access to accommodate disabled visitors;
  • Installation of log burner;
  • 'Walk-through' and deep clean;
  • Sign-off by the Local Authority;
  • Address registration with Royal Mail and BT.

We have our fingers crossed for the end of next month. 

We're not sure why progress has been minimal but here is an update to the above:

  • Outside access to accommodate disabled visitors - the guys doing the driveway are also going to put in some gate-posts and they decided that the posts need to be done before the rest of the drive can be laid. To get the sizes exact, they want to wait until the gates are delivered - the gates are on order but are not scheduled for delivery for another few weeks yet. However, they've made a great job of the round-the-house paving - see photo;

  • Installation of log burner - YAY! Done - see photo;

  • 'Walk-through' and deep clean - obviously the last thing is to clean and this is best left (apparently) until the drive is paviors rather than mud;

  • Sign-off by the Local Authority - YAY! Building Regs are signed off, subject to a couple of provisos;

  • Address registration with Royal Mail and BT - in hand.
So we're still saying that we have our fingers crossed for the end of next month. (Do I sound just a bit fed up?) 

Anyway, the latest photographs are below.

Log Burner

Patio Paving

More soon...

Friday 26 February 2021

Our New Build House Project is almost complete!

The only things to be finished before we are able to move in are: 

  • Outside access to accommodate disabled visitors;
  • Installation of log burner;
  • 'Walk-through' and deep clean;
  • Sign-off by the Local Authority;
  • Address registration with Royal Mail and BT.

We have our fingers crossed for the end of next month. At this stage, before furniture goes in, we intend to walk round with a smart phone and video the result of all the work to date. There will still be odds and ends still to do but these are non-essential and we don't want to wait forever so they can be mini-projects once we are living there. 

Other than that, the hold-ups are just long lead-times for the out-buildings we are ordering (e.g. the carport and a shed) plus the gates. These vary between 8 weeks and 14 weeks. 

Meanwhile, around the portaloo, we have pallets of paving ready to go down next week.