Tuesday 3 November 2020

Current Building Project Update (pre-lockdown2)

The new stairs are in! It's so much easier than using a wobbly old ladder. 

Prior to the stairs being installed, the plumbers managed (I don't know how) to take the slipper bath to the first floor - it took them the best part of two hours! They've positioned the bath and basin taps and their next job will be to fit the Quooker and Belfast sink in the kitchen plus the tap and sink in the utility, as these have all been delivered.

Slipper Bath - Image from Supplier's Website

Showers

We are still unable to install the showers, for two reasons. We have the shower units but they can't go on the wall until the shower wall panels have been delivered. One shower tray has been on order for weeks and we have had the date moved back two or three times - they are now saying December. We can't trust this company not to delay it further so we are cancelling the order and choosing a new shower which we hope to have sometime next week.

The other shower tray has been on site for weeks. Unfortunately, when the plumbers began to install this one, the drain in the shower tray made it unuseable, as it was sited on two load-bearing joists. We have ordered a replacement tray but, unfortunately, the supplier does not arrange collections. Trying to send this back is proving costly as it is over 50% of the refundable amount so... would anyone like to buy a shower tray?

Kitchen worktop

We decided to use a local company that we have used before. Cawdor Stone in Knebworth is a family business, situated next to Lessiters (chocolatiers). Making a choice that complemented the white hob and mid-grey units was difficult but Graeme at Cawdor was very helpful (as well as knowledgeable), letting us take a few samples away to try out. It's only a few minutes from their showroom to the site so swapping samples was relatively painless. Their prices were reasonable too. We have booked a date for the templating and installation will be a week later.

Round-up of other items - our tasks

  • We are meeting with the 'sparks' this week to finalise the lights and light-switches, a pop-up socket in the island plus any other visible electrical bits and bobs.

  • There are no bathroom units, even though we have the basin and taps. We need to measure up tomorrow before the next lockdown so that we can get them on order. We'll probably use Howdens again.
  • The built-in wardrobe frame is in place but we need to buy some doors - one of which has to be cut on a slant because of the sloping ceiling - we're seeking advice from the 'chippies'.

  • We need to buy sliding doors to hide the works in the utility room - boiler, water softener, water tank, etc. We started with Magnet trade but have found similar doors for half that price elsewhere - we are currently looking further into this prior to ordering.

  • The company who will be installing the log burner has already installed the granite hearth but we want the edges rounded, which we hope they can do without too much difficulty.

  • We've started to look at aggregates/slabs/whatever for the driveway and patio. These must be porous in accordance with building regs/planning permission and must also enable people with mobility issues to easily access the house from a car (e.g. high piles of loose gravel is not suitable for wheelchair users).
In hand: Flooring is scheduled for the week commencing 17th November. The worktop is to be installed the following week. The internal doors - about 15 of them - will be hung after the flooring is completed.

Still to be addressed: As listed above plus chasing up other orders as supplies are getting tighter plus the company who were supposed to connect the gas didn't turn up, so we're trying to resolve this as urgently as possible.
 
There are probably quite a few more things that will come up on a daily basis. 

Next instalment scheduled for the end of the month!